Print Reading Mode Back to Calendar Return
  Consent-General Government   # 13.       
Board of Supervisors General Services  
Meeting Date: 09/01/2020  
Brief Title:    Project Budget Increase for Knights Landing Boat Launch Improvement Project
From: Kevin Yarris, Director, General Services
Staff Contact: Jeff Anderson, Sr. Parks Planner, General Services, x5038
Supervisorial District Impact:

Subject
Approve project budget increase of $357,123 to the Knights Landing Boat Launch Improvement Project, for a total project budget of $2,131,740, and approve third amendment to the work authorization under Agreement No. 17-75 with APTIM for construction and engineering support associated with the Knights Landing Boat Launch Improvement Project increasing the amount by $4,018 for a total amount not-to-exceed $149,031. (No general fund impact) (Yarris/Anderson)
Recommended Action
  1. Approve project budget increase of $357,123 to the Knights Landing Boat Launch Improvement Project, for a total project budget of $2,131,740; and
     
  2. Approve third amendment to the work authorization under Agreement No. 17-75 with APTIM for construction and engineering support associated with the Knights Landing Boat Launch Improvement Project increasing the amount by $4,018 for a total amount not-to-exceed $149,031.
Strategic Plan Goal(s)
Robust Economy
Reason for Recommended Action/Background

On January 14, 2020, the Board of Supervisors approved a total project budget of $1,774,617 for the Knights Landing Boat Launch Improvement Project. The Parks Division requests that the Board approve a new total project budget of $2,131,740 to account for increases to actual and estimated project costs. Though the requested total project budget is $2,131,740, the project costs are expected to be $1,871,635. The cost increase is due to the following: in-lieu mitigation payment for impacting water of the United States ($35,000); concrete testing and inspection services ($25,000); Yolo County building permit fees ($18,000); Yocha Dehe cultural monitoring ($15,000), and additional engineering services ($4,018).
 
This action will allow the Director of General Services to spend up to $2,131,740 should any unexpected costs arise. Any additional project expense in excess of the $1,674,617 up to $2,131,740 will be reimbursed by a federal Sport Fish Restoration Act (SFRA) grant. SFRA funding is administered by the Wildlife Conservation Board, and Yolo County is a subrecipient of the federal grant award. The county can request reimbursement of project costs through the SFRA grant in arrears after all grant funds from Wildlife Conservation Board are expended.
 
APTIM has served as the engineer of record on the Knights Landing Boat Launch Improvement Project since January 2018, when they were hired to recreate the original design and construction plans after the previous engineering firm was nonresponsive. APTIM’s continued services are needed in order to provide construction support and prepare engineered drawings to respond to permitting requirements. The additional cost of this third amendment to work authorization utilizing Agreement No. 17-75 is not to exceed $4,018, which brings the work authorization total to $149, 031. This additional cost is within the proposed total budget amount and expenditures will be reimbursed through the SFRA grant. No additional funding is being requested at this time.  
 
Construction is on schedule and is expected to be completed on or before October 30, 2020. Major site improvements completed thus far include installation of the precast vault restroom, concrete walkway, infiltration basin for capturing water runoff, new parking stalls adjacent to the ramp, water well for irrigation and future park host, and widening of the ramp to accommodate new concrete panels. Installation of rip rap along the slough bank is expected to have been installed prior to the September 1 Board of Supervisors hearing.

The updated project budget for this project is as follows:
 

Permitting Expenditures  
Construction $1,438,500
Engineering $149,031
Permitting $249,500
Contingency $294,709
Total Project Expenditures $2,131,740
Project Revenues                 
WCB Grant Funding $1,435,000
SFRA Federal Funding $457,123
County Match $239,617
Total Project Revenue $2,131,740

 

Collaborations (including Board advisory groups and external partner agencies)
County Administrator's Office; Department of Financial Services, County Counsel.
Competitive Bid Process
Request for Proposals (RFP) Service Requested: Knights Landing Boat Launch Improvement Project. An RFP for construction was released in October 2019 and two bids were received. The construction contract with the low bidder, Syblon Reid, in the amount of $1,255,000 was approved by the Board of Supervisors on January 14, 2020.
Attachments
Att. A. APTIM Work Authorization
Att. B. APTIM Additional Cost Proposal

Form Review
Inbox Reviewed By Date
Financial Services mpatterson 08/24/2020 04:09 PM
County Counsel Hope Welton 08/25/2020 12:31 PM
Form Started By: Jeff Anderson Started On: 08/17/2020 12:45 PM
Final Approval Date: 08/26/2020

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.