Print Reading Mode Back to Calendar Return
  Consent-Community Services   # 24.       
Board of Supervisors   
Meeting Date: 09/25/2018  
Brief Title:    Accept Utility Location Services Contract
From: Taro EchiburĂș, Director, Department of Community Services
Staff Contact: James Flynn, Associate Civil Engineer, Department of Community Services, x8436
Supervisorial District Impact:

Subject
Accept as complete the County Road 98 Bike & Safety Improvement – Phase II Utility Location Potholing Services contract, performed under Agreement No. 5555-2018-3011 NOR-CAL with Nor-Cal Pipeline Services. (No general fund impact) (Echiburu/Flynn)
Recommended Action
  1. Accept as complete the CR 98 Bike & Safety Improvement – Phase II Utility Location Potholing Services Contract performed under Agreement No. 5555-2018-3011 NOR-CAL with Nor-Cal Pipeline Services; and 
     
  2. Authorize the Director of Public Works to sign and record the Notice of Completion.
Strategic Plan Goal(s)
Thriving Residents
Safe Communities
Sustainable Environment
Reason for Recommended Action/Background
Nor-Cal Pipeline Services completed underground utility locating services on November 3, 2017 in accordance with the contract plans and specifications.  The Board of Supervisors’ acceptance of the work will allow the Notice of Completion to be recorded and the project to be formally closed out.
 
Background
 
The CR 98 Phase II project extended the improvements, completed in the initial Phase in 2014, between Woodland and County Road 29, southward to the Solano County line.  The project received federal transportation funding for preliminary engineering and project development through the Sacramento Area Council of Governments (SACOG) in the amount of $1,593,400.
 
Part of project development was to locate existing underground utilities within the project area in order to determine which, if any, underground utilities must be relocated as part of the eventual road construction.
 
The Board of Supervisors authorized the Director of Public Works to execute a utility locating contract to the lowest responsive bidder on July 18, 2017. 
 
Five bids were received at the bid opening on July 11, 2017. The underground locating services contract was awarded to the lowest bidder, Nor-Cal Pipeline Services in the amount of $146,308. Work began September 18, 2017 and was completed on November 3, 2017. A total of 212 exploratory holes were excavated.
 
The contract was left open between November 2017 and September 2018 to give the County the opportunity to further investigate underground utilities, if needed.  No additional utility excavations are needed at this time. The contract is ready to be accepted as complete.
Collaborations (including Board advisory groups and external partner agencies)
University of California, Davis staff assisted with the location of underground utilities within the project area.
Competitive Bid Process
N/A
 

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   133,555
Amount budgeted for expenditure:    $   300,000
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$133,555
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
Federal transportation funds will reimburse the road fund for 88.53% of the cost or $118,236.24 with a local match of 11.47% or $15,318.76.  Funds were expended during FY 2017/18.
Attachments
Att. A. Location Map
Att. B. Notice of Completion

Form Review
Inbox Reviewed By Date
Financial Services bporter 09/17/2018 07:53 AM
County Counsel Hope Welton 09/18/2018 09:06 AM
Form Started By: dcomingore Started On: 09/05/2018 10:40 AM
Final Approval Date: 09/18/2018

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.