  Consent-General Government   # 12.       
Board of Supervisors County Administrator  
Meeting Date: 09/11/2018  
Brief Title:    Work Authorization for Esparto Community Park & Aquatic Center
From: Patrick Blacklock, County Administrator
Staff Contact: Jill Cook, Deputy County Administrator, County Administrator's Office, x8699
Supervisorial District Impact:

Subject
Authorize the Assistant County Administrator or her designee to execute a work authorization under existing Agreement No. 17-68 with Architectural Nexus for design of the Esparto Community Park and Aquatic Center in an amount not to exceed $92,155. (No general fund impact) (Blacklock/Cook)
Recommended Action
Authorize the Assistant County Administrator or her designee to execute a work authorization under existing Agreement No. 17-68 with Architectural Nexus for design of the Esparto Community Park and Aquatic Center in an amount not to exceed $92,155.
Strategic Plan Goal(s)
Thriving Residents
Reason for Recommended Action/Background
On May 9, 2017, the County Board of Supervisors authorized the Assistant County Administrator or her designee to execute a work authorization under Agreement No. 14-206 with Architectural Nexus to design the Esparto Community Park and Aquatic Center project in an amount not to exceed $281,600. Work Authorization #1 was approved under Agreement No. 14-206 in the amount of $56,100.

A Request for Qualifications (RFQ) was conducted in January 2017 by General Services for On-Call Consultants which created a new agreement (Agreement No. 17-68). The County Board of Supervisors approved Agreement No. 17-68 on May 9, 2017. The term of the agreement is July 1, 2017 to June 30, 2020. Work Authorization #2 was approved under this new agreement in the amount of $225,500. The total of the two approved work authorizations is $281,600, the maximum authorized by the County Board of Supervisors.

Architectural Nexus' work on project planning and design is more than anticipated due to changes in project scope. Scope of service changes and needs included additional efforts for architectural and civil engineering services as well as additional scope needs.
 
Service Amount
Architect $49,470
Civil Engineer $32,585
Additional Scope $4,600
TOTAL $86,655

 See Attachment A for an itemized list of additional efforts and services.

The total for Work Authorization #3 is $86,655. Authority for an additional $5,500 is requested to serve as a contingency for any future project design needs. A new work authorization would be approved by staff for use of any of this funding. All costs will be covered by the existing project budget contingency.
 
Service Amount
Architect $49,470
Civil Engineer $32,585
Additional Scope $4,600
Contingency $5,500
TOTAL $92,155

Work Authorization #3 and the $5,500 contingency funding will bring the project total with Architectural Nexus to $373,755.
 
Item Amount
Work Authorization #1 $56,100
Work Authorization #2 $225,500
Work Authorization #3 $86,655
Contingency – Phase 4 $5,500
TOTAL $373,755
Collaborations (including Board advisory groups and external partner agencies)
Project Development Team, Kitchell CEM, County Counsel, District 5, Esparto Unified School District.
Competitive Bid Process
RFQ issued by the General Services Department in January 2017 for on-call consultant list. County Board of Supervisors approved On-Call Consultant List on May 9, 2017.

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   92,155
Amount budgeted for expenditure:    $   92,155
Additional expenditure authority needed:    $  
One-time commitment     Yes
Source of Funds for this Expenditure
$92,155
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
The work authorization will be funded by the existing project budget contingency.
Attachments
Att. A. Work Authorization Phase 3

Form Review
Inbox Reviewed By Date
Financial Services Tom Haynes 09/04/2018 08:11 PM
County Counsel Hope Welton 09/05/2018 03:15 AM
Form Started By: dwhitehead Started On: 06/19/2018 02:28 PM
Final Approval Date: 09/05/2018

    