  Consent-General Government   # 10.       
Board of Supervisors County Administrator  
Meeting Date: 03/21/2017  
Brief Title:    First Amendment to Contract with CBEC Ecoengineering for Engineering Services
From: Patrick Blacklock, County Administrator
Staff Contact: Elisa Sabatini, Natural Resources Manager, County Administrator's Office, x5773

Subject
Approve amendment to Agreement No. 17-03 with CBEC Ecoengineering for data collection and analysis services to fulfill the terms of a grant agreement with the California Department of Fish and Wildlife for the County's Westside Tributaries Flow Monitoring project. (No general fund impact) (Blacklock/Sabatini)
Recommended Action
Approve amendment (Attachment B) to Agreement No. 17-03 with CBEC Ecoengineering for data collection and analysis services to fulfill the terms of a grant agreement with the California Department of Fish and Wildlife for the County's Westside Tributaries Flow Monitoring project.
Strategic Plan Goal(s)
Safe Communities
Sustainable Environment
Flourishing Agriculture
Reason for Recommended Action/Background
On January 10, 2017 the Board approved a three year contract for $208,870 with CBEC Ecoengineering (Att. A, staff report and approved contract) for Yolo Bypass tributary flow monitoring services as part of the County's "Westside Tributaries Flow Monitoring Project", funded through a Proposition 1 grant award by the California Department of Fish and Wildlife. The total grant award is $331,148 (Agreement # P1596031).  

The reason for this amendment is because staff inadvertently used the incorrect budget schedule when drafting the CBEC contract that was approved by the Board in January 2017. The approved contract's budget is $208,870.  The correct budget/contract amount is $280,983.  

Staff recommends that the Board approve the amendment (Attachment B) to Contract #17-03 with CBEC Ecoengineering, increasing the total compensation by $72,113, for a total contract value of $280,983.  The additional  $72,113 is reimbursable by the California State Department of Fish and Wildlife. There are no general funds associated with this request nor with the project. No additional expenditures are expected this fiscal year and the remaining fund balance on the contract will be accounted for in future years' budgets.
Collaborations (including Board advisory groups and external partner agencies)
Staff has collaborated with the California Department of Fish and Wildlife, County Counsel, and Department of Financial Services.

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   72,113
Amount budgeted for expenditure:    $   100,000
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$0
$72,113
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
There is no fiscal impact associated with this request in the current fiscal year; expenditures are expected to remain at less than or equal to the adopted budget resolution of $100,000 for FY16/17.  All contracted services are reimbursable through the County's grant agreement with the California Department of Fish and Wildlife ( Agreement # P1596031).  The balance of the contract (FY's 17/18 and 18/19) expenditures will be included in the appropriate years' budgets.
Attachments
Att. A. Agr. No. 17-03
Att. B. Amendment

Form Review
Inbox Reviewed By Date
Phil Pogledich Phil Pogledich 03/15/2017 09:22 AM
Financial Services Tom Haynes 03/16/2017 01:34 PM
Form Started By: Elisa Sabatini Started On: 03/01/2017 09:14 AM
Final Approval Date: 03/16/2017

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.