  Consent-Community Services   # 19.       
Board of Supervisors   
Meeting Date: 02/20/2018  
Brief Title:    Accept as complete the County Road 99W Bridge Replacement Over Buckeye Creek
From: Taro EchiburĂș, AICP, Director, Department of Community Services
Staff Contact: Mark Christison, Associate Civil Engineer, Department of Community Services, x8842
Supervisorial District Impact:

Subject
Accept as complete the construction work on the County Road 99W bridge replacement over Buckeye Creek performed under Agreement 5555-2017-3011-16220 by Viking Construction Co., Inc. (No general fund impact) (Echiburu/Christison)
Recommended Action
  1. Accept as complete the construction work on the County Road 99W bridge replacement over Buckeye Creek performed under Agreement 5555-2017-3011-16220 by Viking Construction Co., Inc.; and
     
  2. Authorize the Director of Public Works to sign and record the Notice of Completion.
Strategic Plan Goal(s)
Operational Excellence
Thriving Residents
Safe Communities
Sustainable Environment
Flourishing Agriculture
Reason for Recommended Action/Background
REASON FOR RECOMMENDED ACTIONS
 
Viking Construction Co., Inc. substantially completed construction of this project on January 12, 2018 in accordance with the contract plans and specifications.  The Board of Supervisors’ acceptance of the work, and authorization for the Director of Public Works to record the Notice of Completion, will allow the project to be closed out and final payment to be made to the contractor.   
 
BACKGROUND
 
The bridge is located on County Road 99W over Buckeye Creek, approximately 0.48 mile southeast of County Road 1 near the community of Dunnigan.  The project replaced an old bridge that Caltrans had classified  as structurally deficient and scour critical, with a sufficiency rating of 32.5 out of 100.   The new bridge is wider than the old, and the added width will improve safety.  The new bridge will be able to carry extra-legal truck loads, and eliminates a long detour for these types of permit loads that are diverted from nearby Interstate 5.   The new bridge has no footings in the creek, which will reduce environmental impacts to the creek.    
 
The Board of Supervisors approved the plans and specifications for the replacement of this bridge on February 21, 2017, and authorized the Department to advertise for bids and award a contract to the lowest responsive bidder   
 
Following the receipt of construction authorization from Caltrans, the Department of Community Services advertised the project.  Four bids were received at the bid opening on May 3, 2017, ranging from $2,520,035 to $2,867,000.  Viking Construction was the lowest bidder and  was awarded the contract on May 12, 2017.  Following receipt of the contractor’s bond and insurance certificates, the contract was executed on May 25, 2017.  
 
Work began on June 9, 2017, and progressed through the summer construction season. The structure was substantially completed in December of 2017, and was opened to public traffic on January 5, 2018
 
The project was completed without any claims or change orders, and within the authorized budget.  The cost of the contract, as well as County staff costs to administer and inspect the project, will be 100% reimbursed with federal Highway Bridge Program funds administered by Caltrans.  
 
Collaborations (including Board advisory groups and external partner agencies)
Federal Highway Administration
Caltrans
Sacramento Area Council of Governments (SACOG)
California Department of Fish and Wildlife
California Regional Water Quality Control Board
U.S. Fish and Wildlife Service
U.S. Army Corps of Engineers
 
Competitive Bid Process
The project was publicly advertised on March 13, 2017
The sealed bids received were publicly opened on May 3, 2017
Bids Received

Viking Construction

$2,520,035.70

Myers and Sons Construction

$2,759,090.60

RA Nemetz Construction

$2,781,461.00

Steelhead Constructors

$2,867,000.00


Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   2,521,920
Amount budgeted for expenditure:    $   3,448,000
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$2,521,920
Attachments
Att. A. Location Map
Att. B. Notice of Completion
Att. C. Project Photos

Form Review
Inbox Reviewed By Date
Financial Services bporter 02/12/2018 03:47 PM
County Counsel Hope Welton 02/12/2018 03:54 PM
Form Started By: Mark Christison Started On: 01/30/2018 08:48 AM
Final Approval Date: 02/12/2018

    