  Consent-General Government   # 14.       
Board of Supervisors General Services  
Meeting Date: 11/20/2018  
Brief Title:    Approve $199,000 Budget for Monroe Detention Center Showers
From: Kevin Yarris, Director, General Services
Staff Contact: Laura Liddicoet, Sr. Administrative Services Analyst, General Services, x4881
Supervisorial District Impact:

Subject
Approve $199,000 project budget for renovations and improvements associated with the flooring at the Monroe jail showers and drying area. (No general fund impact) (Yarris)
Recommended Action
Approve $199,000 project budget for renovations and improvements associated with the flooring at the Monroe jail showers and drying area.
Strategic Plan Goal(s)
Operational Excellence
Safe Communities
Reason for Recommended Action/Background
In previous years, both the General Services Department and Sheriff's Office have identified the need for renovation and improvements to be made to thirty-two existing shower stalls located at the Monroe Detention Center.  The location is currently experiencing failing tiles on the ceilings and floors, aged grout, and issues related to the failure of the existing plumbing features.

General Services plans to remove the existing tiles, install new stainless steel shower pans, epoxy and better protect the walls, and install new plumbing features. Bids for this work have not yet been sought, as General Services plans to update two stalls in this manner initially, confirming the success of the installation prior to beginning improvements on the remaining thirty stalls.  General Services will comply with all Department of Financial Services Procurement policies in contracting of this work, and will return to the Board for contract approval, if required.

Funding for this project has been budgeted in the 2018-2019 Accumulated Capital Outlay (ACO) budget:
 
Project Expenditures  
Shower Renovation and Improvements $143,000
Abatement Testing $6,000
Project Management $20,000
Contingency $30,000
Total Project Expenditures $199,000
   
Project Revenues  
Accumulated Capital Outlay (ACO) $199,000
Total Project Revenues $199,000
Collaborations (including Board advisory groups and external partner agencies)
County Counsel, Department of Financial Services, County Administrator's Office, Yolo County Sheriff, General Services
Competitive Bid Process
Bids for this work have not yet been sought. General Services will return to the Board of Supervisors for contract approval for this work, should it be required in compliance with Department of Financial Services Procurement policies.

Fiscal Impact
No Fiscal Impact
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   199,000
Amount budgeted for expenditure:    $   199,000
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$199,000
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
Funding for this project was secured through the Accumulated Capital Outlay budget for the 2018-2019 fiscal year.
Attachments
No file(s) attached.

Form Review
Inbox Reviewed By Date
Elisa Sabatini Elisa Sabatini 11/13/2018 09:59 AM
Financial Services (Originator) mpatterson 11/13/2018 10:17 AM
County Counsel Hope Welton 11/13/2018 12:51 PM
Form Started By: Laura Liddicoet Started On: 05/15/2018 12:31 PM
Final Approval Date: 11/13/2018

    