  Consent-General Government   # 18.       
Board of Supervisors General Services  
Meeting Date: 11/20/2018  
Brief Title:    Yolo County Historical Courthouse Improvement Project
From: Kevin Yarris, Director, General Services
Staff Contact: Laura Liddicoet, Sr. Administrative Services Analyst, General Services, x4881
Supervisorial District Impact:

Subject
Approve total project budget of $12,694,109 for design, engineering, abatement, construction and improvements to the Yolo County Historical Courthouse; adopt budget resolution adjusting the Yolo County Historical Courthouse budget to reflect an increase of $7,285,281; approve contract with Arntz Builders for construction work associated with the Yolo County Historical Courthouse Renovations for $7,453,146 through September 30, 2019; and authorize the Director of General Services to amend the construction contract with Arntz Builders up to an additional $745,315, and to extend the contract through December 31, 2019 should amendments be required by the scope of the project. (General fund impact $2,000,000) (4/5 vote required) (Yarris/Nunes)
Recommended Action
  1. Approve total project budget of $12,694,109 for design, engineering, abatement, construction and improvements to the Yolo County Historical Courthouse;
     
  2. Adopt budget resolution adjusting the Yolo County Historical Courthouse budget to reflect an increase of  $7,285,281;
     
  3. Approve contract with Arntz Builders for construction work associated with the Yolo County Historical Courthouse Renovations for $7,453,146 through September 30, 2019; and
     
  4. Authorize the Director of General Services to amend the construction contract with Arntz Builders up to an additional $745,315, to extend the contract through December 31, 2019 should amendments be required by the scope of the project.
Strategic Plan Goal(s)
Operational Excellence
Thriving Residents
Sustainable Environment
 
Reason for Recommended Action/Background

On July 1, 2015, the Superior Court of California vacated the Historic Yolo County Courthouse, located at 725 Court Street in Woodland, in order to occupy their new facility. Earlier in 2015, the Jacobs Strategic Space Utilization Study, which was adopted and approved by the Board of Supervisors, identified the Historic Courthouse as the primary headquarters for the Probation Department's Administrative staff. After a series of initial demolition, unexpected abatement, and revisions to design and engineering documentation, the building is ready for the construction phase.

In September 2018, a request for proposal was advertised for the general construction phase of this project. Three responses were received in late October, with Arntz Buiders successfully earning the contract. The contract issued to Arntz Builders is for the dollar amount identified in response to the request for proposal ($7,453,146) however, the General Services Department is requesting authorization for the Director of General Services to issue amendments to their contract should the scope of work need to be altered. Amendments in excess of an additional $745,315 (10% construction contingency) will be brought back to the Board of Supervisors for approval.

As mentioned above, the renovation of the Historic Courthouse was identified as a possible solution to specific space and infrastructure needs for Yolo County in the Jacobs strategic space utilization study. The project was approved by the Board of Supervisors on May 31, 2016, with additional financing requirements being addressed through the Yolo County Public Agencies Financing Authority 2017 Lease Revenue Bond Issuance.  The original project budget that was approved for work to begin in 2017 was $5,000,000 knowing the ultimate cost would likely exceed $10,000,000.  Now that abatement and demolition is complete and the bid has closed, the final budget is as follows: 
 

Project Expenditures  
Architectural/Engineering $980,595
Construction $9,524,646
Furniture, Fixtures, IT, Telecommunications $974,858
Project Management $60,000
Project Contingency (10% of total project) $1,154,010
Total Project Expenditures $12,694,109
   
Project Revenues  
CIP Bond Proceeds $6,000,000
CIP Reserve $2,500,000
General Fund $2,000,000
Accumulative Capital Outlay Fund $1,500,000
Development Impact Fees $600,000
Interest Earnings $94,109
Total Project Revenues $12,694,109
 
Additional funding in excess of the original project budget has been identified through anticipated savings in the Monroe jail expansion project, the CIP reserve, General Fund CIP dollars included in the 2018-19 Adopted Budget, Development Impact Fees and available balances in the ACO fund.  The project is scheduled for completion in late August 2019, with re-occupancy following shortly thereafter.
Collaborations (including Board advisory groups and external partner agencies)
County Administrator's Office, Department of Financial Services, County Counsel, Probation Department, General Services Department.
Competitive Bid Process
Request for Proposals, Service Requested: Yolo County Historic Courthouse Renovation

Bids Received:
 
Bidder Bid
Arntz Builders $7,453,146
DL Faulk $8,387,000
Diede Construction $8,159,060

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   12,694,109
Amount budgeted for expenditure:    $   4,200,000
Additional expenditure authority needed:    $   7,285,281
One-time commitment     Yes
Source of Funds for this Expenditure
$2,500,000
$2,000,000
$894,612
$1,260,058
$30,611
$600,000
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
The originally approved and funded budget for this project was $5,000,000. Project expenditures in 2016-17 and 2017-18 totaled $1,208,828, while the 2018-19 Adopted Budget included an appropriation of $4,200,000. At this time General Services is requesting additional funding in the amount of $7,285,281 to complete improvements to the Yolo County Historical Courthouse.

The attached budget resolution reflects the recommended increase to the Courthouse project budget, as well as the ancillary appropriation adjustments that are needed to transfer funds into the project. The General Fund portion of $2,000,000 was previously included in the 2018-19 Adopted Budget.
Attachments
Att. A. Budget Resolution
Att. B. Agreement
Att. C. Bid Documents
Att. D. Presentation

Form Review
Inbox Reviewed By Date
Financial Services (Originator) Tom Haynes 11/15/2018 03:51 PM
County Counsel Phil Pogledich 11/15/2018 04:13 PM
Form Started By: Laura Liddicoet Started On: 04/30/2018 08:14 AM
Final Approval Date: 11/15/2018

    