Print Reading Mode Back to Calendar Return
  Consent-Community Services   # 25.       
Board of Supervisors   
Meeting Date: 01/29/2019  
Brief Title:    Accept County Road 27 Rehabilitation Project
From: Taro Echiburu, Director, Department of Community Services
Staff Contact: Mark Christison, Associate Civil Engineer, Department of Community Services, x8842
Supervisorial District Impact:

Subject
Accept as complete the construction work on the County Road 27 Rehabilitation Project performed under Agreement 5555-2019-3011-LAMON CR27 by Lamon Construction. (No general fund impact) (Echiburu)
Recommended Action
  1. Accept as complete the construction work on the County Road 27 Rehabilitation Project performed under Agreement 5555-2019-3011-LAMON CR27 by Lamon Construction; and
     
  2. Authorize the Director of Public Works to sign and record the Notice of Completion.
Strategic Plan Goal(s)
Thriving Residents
Flourishing Agriculture
Reason for Recommended Action/Background
Lamon Construction completed construction of this project on November 21, 2018 in accordance with the contract plans and specifications.  The Board of Supervisor's acceptance of the work, and authorization for the Director of Public Works to record the Notice of Completion, will allow the project to be closed out and final payment to be made to the contractor.   
 
Background
The segments of County Road (CR) 27 improved are shown on the location map (see Attachment A) and are listed below:
 
  1. CR 27 from one mile west of CR 92D to CR 93
  2. CR 27 from CR 94 to CR 95
  3. CR 27 from CR 97 to CR 98
The existing pavement on these sections of CR 27 had far exceeded its design life.  It required extensive and frequent maintenance.  The pavement replacement work included two basic strategies:
  1. Completely recycle the existing asphalt and base course in-place, add supplemental aggregate base as needed and treat with cement, and overlay with hot mix asphalt.
  2. Pulverize pavement in-place, add supplemental aggregate base, grade, compact and repave with asphalt concrete.
Segments 2 and 3 were funded with federal funds awarded to the County through SACOG’s competitive "2015 Regional/Local Funding Program".  Segment 1 was one of the sites identified in the “2018 Pavement Preservation Project” included in the final fiscal year 2017-18 budget adopted on September 26, 2017.  Because of the proximity and similar equipment needed to do these three segments, they were combined to facilitate construction and minimize the duration of road closure. (The plans and specifications for the balance of the 2018 Pavement Preservation Project were previously approved for bidding at the April 24, 2018 Board meeting.) 
 
The Board of Supervisors approved the plans and specifications for the County Road 27 Rehabilitation Project on May 8, 2018, and authorized the Department to advertise for bids and award a contract to the lowest responsive bidder  
 
Following the receipt of construction authorization from Caltrans, the Department of Community Services advertised the project. 

Work began on September 17, 2018, and progressed through the construction season. The project was substantially completed in November of 2018, and CR27 opened to public traffic on November 16, 2018
 
The project was completed without any claims or change orders, and within the authorized budget.
Collaborations (including Board advisory groups and external partner agencies)
SACOG awarded federal funds for Segments 2 and 3.  
Caltrans administers the federal funds for the project.
Competitive Bid Process
The competitive bid process was completed in accordance with state and federal laws.  The project was advertised on June 5, 2018, and bids were opened and read publicly at the Department of Community Services on July 10, 2018.  Three bids were received at the bid opening on July 10, 2018, ranging from $2,678,540 to $3,317,305.  Lamon Construction was the lowest bidder and was awarded the contract on July 26, 2018.  Following receipt of the contractor’s bond and insurance certificates, the contract was executed on July 30, 2018.

Bids Received
 
Bidder Bid
Lamon Construction
$2,678,539.78
Northwest Paving
$3,195,123.00
Teichert Construction $3,317,305.50

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   2,705,000
Amount budgeted for expenditure:    $   3,353,000
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$2,705,000
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
The estimated final cost of construction is approximately $2,705,000 including payments to the contractor, construction engineering, and testing.  Federal transportation funds will reimburse $1,563,800 of that amount with the remaining $1,141,200 funded by the Road Fund.
Attachments
Att. A. Location Map
Att. B. Notice of Completion
Att. C. Project Photos

Form Review
Inbox Reviewed By Date
Financial Services bporter 01/15/2019 10:25 AM
County Counsel Hope Welton 01/18/2019 05:01 PM
Form Started By: Mark Christison Started On: 12/21/2018 03:39 PM
Final Approval Date: 01/18/2019

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.