  Consent-General Government   # 22.       
Board of Supervisors General Services  
Meeting Date: 05/21/2019  
Brief Title:    Historic Courthouse Renovation
From: Kevin Yarris, Director, General Services Department
Staff Contact: Laura Liddicoet, Sr. Administrative Services Analyst, General Services, x4881
Supervisorial District Impact:

Subject
Approve amending the construction contract with Arntz Builders increasing compensation up to an additional $254,685 for a total amendment authorization of $1,000,000 for improvements related to the Yolo County Historical Courthouse. (No general fund impact) (4/5 vote required) (Yarris)
Recommended Action
Authorize the Director of General Services to amend the construction contract with Arntz Builders up to an additional $254,685 for a total amendment authorization of $1,000,000 for improvements related to the Yolo County Historical Courthouse.
Strategic Plan Goal(s)
Operational Excellence
Safe Communities
 
Reason for Recommended Action/Background
At the November 20, 2018 Board of Supervisors meeting, a $7,453,146 contract with Arntz Builders for improvements related to the Yolo County Historical Courthouse was approved.  This action also allowed for the Director of General Services to amend the construction contract with Arntz Builders up to an additional $745,315 and to extend the contract though December 31, 2019 should amendments be required by the scope of the project.  At this time, identified change orders and additional work items have been identified, requiring an increase to the dollar value of the Director of General Services ability to amend the construction contract with Arntz. 

This request for increase is specifically related to low voltage work that is now required by the project, but was not anticipated at the time of bidding for the construction project.  The cost for this work is estimated to be approximately $250,000 itself.  Other noted increases to the project include additional demolition of the third and fourth floors, additional interior wall insulation, and fire rating requirements.  Performing the demolition of those additional floors now rather than later will save in costs and will also create less disturbance for Probation staff by completing it prior to Probation moving in.

Escalation in construction costs outside of the original amendment authorization amount was planned for, and the project remains on schedule and within the overall project budget of $12,694,109.
Collaborations (including Board advisory groups and external partner agencies)
County Administrator's Office, County Counsel, Department of Financial Services
Competitive Bid Process
N/A

Fiscal Impact
No Fiscal Impact
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   254,685
Amount budgeted for expenditure:    $   254,685
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$254,685
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
Construction escalation was planned for in development of the project budget. The project does not currently anticipate requiring additional funding.
Attachments
No file(s) attached.

Form Review
Inbox Reviewed By Date
Elisa Sabatini Elisa Sabatini 05/13/2019 01:50 PM
Financial Services (Originator) mpatterson 05/13/2019 01:54 PM
County Counsel Hope Welton 05/13/2019 05:00 PM
Form Started By: Laura Liddicoet Started On: 04/29/2019 07:43 AM
Final Approval Date: 05/13/2019

    