Print Reading Mode Back to Calendar Return
  Consent-Affiliated Agencies   # 12.       
Board of Supervisors   
Meeting Date: 04/23/2019  
Brief Title:    Esparto Park & Aquatic Center Contract Amendment
From: Jill Cook, Deputy County Administrator, County Administrator's Office
Staff Contact: Connie Robledo, Associate Management Analyst, County Administrator's Office, x5776
Supervisorial District Impact:

Subject
Approve first amendment to Agreement No. 18-18 with SW Allen Construction Inc. to increase the maximum compensation by $135,214 and extend the project completion date to May 10, 2019 for the Esparto Park and Aquatic Center; adopt budget resolution increasing the total project budget by $649,449; and approve use of Development Impact Fee funds for the contract with SW Allen Construction Inc. (General fund impact $536,441) (4/5 vote required) (Blacklock/Cook)
Recommended Action
  1. Approve first amendment to Agreement No. 18-18 with SW Allen Construction Inc. to increase the maximum compensation by $135,214 and extend the project completion date to May 10, 2019 for the Esparto Park and Aquatics Center;
     
  2. Adopt budget resolution increasing the total project budget by $649,449; and
     
  3. Approve use of Development Impact Fee funds for the contract with SW Allen Construction Inc.
Strategic Plan Goal(s)
Thriving Residents
Reason for Recommended Action/Background
In March 2012, the County was awarded $2,896,000 from California State Parks Office of Grants and Local Services as part of Round Two of the Statewide Park Program for the Esparto Community Park and Aquatic Center project. The grant contract was executed in August 2013 for a grant performance period of July 1, 2011 through June 30, 2019 and a contract performance period from July 1, 2011 through June 30, 2041. On May 19, 2015, the Board of Supervisors adopted a resolution (Resolution No 15-58) approving the Engineer's Report and levying the assessments within the Esparto Park Maintenance and Operations Assessment District. On May 9, 2017, the Board authorized the Assistant County Administrator to execute a work authorization under existing Agreement No. 14-206 with architect, Architectural Nexus, to design the project in an amount not to exceed $281,600. In May 2017, the Yocha Dehe Wintun Nation announced their gift of $1,500,000 to the project to augment the park construction. On September 26, 2017, the Board approved the design and specifications developed by Architectural Nexus and authorized the Deputy County Administrator to advertise for competitive construction bids. Major project elements include the following: a little league baseball/softball field, multi-use playing field (1 adult soccer field, two youth soccer fields or 1 Football Field) full basketball court, two pools (8 lane competitive swimming pool & youth/wading pool), and aquatics building with changing rooms/restrooms, outdoor showers, office, storage room, meeting room, snack bar, and field restrooms, fenced pool equipment area, pedestrian bridge, walking trail,  60 car parking area, and central gathering area. Bids were released on October 9, 2017 and were due on November 7, 2017. Five (5) construction bids were received on November 7, 2017 ranging from $6,288,100 to $7,692,000. The low bidder was SW Allen. 

Construction Contract:
Staff recommends extending the general contractor’s (SW Allen Construction Inc) project completion date due to more rain than anticipated and other unforeseen events during the construction period. Staff also recommends increasing the maximum compensation of the general contractor’s agreement by $135,214. See detailed Construction Cost and Time Summary (Attachment C).

Project Budget:
The original project budget was approved for $7,414,505 and staff recommends an increase of $649,449, for a total project budget of $8,063,954. The adjustment is the result of higher than expected construction costs, design errors and/or omissions, and originally unbudgeted costs including: environmental assessment and special inspections, signage, fencing, water connection fees, parking lot paving/wheel stops and gate, soccer goals, one-time startup costs such as office and maintenance equipment, and a $50,000 closeout contingency for unforeseen additional expenses to complete the project. See detailed Project Budget Summary (Attachment D).
 
Capital project budgets typically include a 10-15% overall contingency; this project included no overall contingency and a 5% construction contingency of $314,405. The revised budget is 13.58% above the base project budget.
 
The strategy to close the budget adjustment includes a $113,167 increase of Park and Bridge Development Impact Fee revenue use and $536,441 CIP Contingency use. A $33,746 reduction in private donation revenue is projected to be offset by a $33,000 payment from the architect and adjustments to other revenues. In addition to appropriating additional collected Development Impact Fee revenue use for the project, the budget resolution adds an appropriation to allow staff to transfer remaining collected Development Impact Fees revenue to the capital project fund that were included in the original project budget and which the Fiscal Year 2018-19 budget omitted. The 2018-19 Adopted Budget included a general appropriation of $2.6 million for CIP Contingency use. Of this amount, $2 million was approved in November 2018 for use on the Historic Courthouse Improvement project. After transferring the requested funds to the Esparto Park & Aquatic Center project, a balance of $63,559 in CIP contingency funds will remain. All project expenses are paid from the project’s designated Capital Project fund and appropriated, collected Development Impact Fees revenues are transferred there for reimbursement as needed.

The Board Subcommittee on Capital Investments reviewed these changes on April 9, 2019 and did not have any concerns about the changes.
Collaborations (including Board advisory groups and external partner agencies)
County Counsel, Department of Financial Services, Board Subcommittee on Capital Investments
Competitive Bid Process
N/A

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   649,449
Amount budgeted for expenditure:    $   536,441
Additional expenditure authority needed:    $   113,167
One-time commitment     Yes
Source of Funds for this Expenditure
$536,441
$113,167
- $159
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
The CIP Contingency is a General Fund set aside for use on approved capital projects.
Attachments
Att. A. Contract Amendment
Att. B. Budget Resolution for DIF
Att. C. Construction Cost & Time Summary
Att. D. Project Budget Summary

Form Review
Inbox Reviewed By Date
Elisa Sabatini Lupita Ramirez 04/17/2019 11:21 AM
Elisa Sabatini Elisa Sabatini 04/17/2019 12:53 PM
Financial Services Tom Haynes 04/17/2019 02:45 PM
County Counsel cscarlata 04/18/2019 03:24 PM
Form Started By: Constance Robledo Started On: 04/09/2019 10:18 AM
Final Approval Date: 04/18/2019

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.