  Consent-General Government   # 20.       
Board of Supervisors General Services  
Meeting Date: 04/23/2019  
Brief Title:    HVAC Control Replacements
From: Kevin Yarris, Director, General Services Department
Staff Contact: Laura Liddicoet, Sr. Adminstrative Services Analyst, General Services, x4881
Supervisorial District Impact:

Subject
Approve $359,101 project budget for transition of HVAC controls from Novar HVAC controls to Delta HVAC Control System at various County owned and operated locations. (No general fund impact) (Yarris)
Recommended Action
Approve $359,101 project budget for transition of HVAC controls from Novar HVAC controls to Delta HVAC Control System at various County owned and operated locations.
Strategic Plan Goal(s)
Operational Excellence
Sustainable Environment
Reason for Recommended Action/Background
Currently General Services operates the HVAC systems on two systems, Novar and Delta.  The current Novar system is no longer supported and if there are any failures, there would be no support from Novar and General Services would not be able to get it back online.  Depending on the time of the year, the system offline may cause issues for temperature control in buildings utilized by staff and customers.  Additionally, operating two systems is not efficient and wastes time and staff productivity. Moving to one system will reduce staff time toggling between two systems and will increase response time to customer requests for temperature adjustments.

Transitions in the controls will occur at the following proposed locations:
  • District Attorney Building
  • Community Services Building
  • Public Defender Building
  • 500 B Jefferson
  • Yolo County Landfill
  • 120 West Main
  • Agriculture Building
  • Central Library
  • Esparto Library
Funding for this project has been budgeted in the 2018-2019 Accumulated Capital Outlay (ACO) budget the Central Library Archives project budget, and the Library 2018-2019 operational budget;
Project Expenditures  
Transition from Novar to Delta HVAC controls $359,101
Total Project Expenditures $359,101
   
Project Revenues  
Accumulated Capital Outlay (ACO) $320,754
Central Library Archives Budget $24,160
Library Operational Budget $14,187
Total Project Revenues $359,101
Collaborations (including Board advisory groups and external partner agencies)
Department of Financial Services, County Administrator's Office, County Counsel, Library, General Services Department
Competitive Bid Process
The General Services Department complies with all Department of Financial Services policies and procedures. Should completion of this work require contracts which require additional Board action, the General Services Department will return to the BOS immediately.  Government Code, Section 4217.10 et seq. allows public agencies to directly contract for energy services that demonstrate the savings exceed the costs.  That justification for this project is attached.

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   359,101
Amount budgeted for expenditure:    $   359,101
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$320,754
$24,160
$14,187
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
Funding for this project was secured through Accumulated Capital Outlay, Central Library Archives Project budget and Library Operational budget for the 2018-19 fiscal year.
Attachments
Att. A. Technical Audit

Form Review
Inbox Reviewed By Date
Financial Services (Originator) mpatterson 04/17/2019 09:54 AM
County Counsel cscarlata 04/17/2019 04:50 PM
Form Started By: Laura Liddicoet Started On: 07/25/2018 11:06 AM
Final Approval Date: 04/17/2019

    