Back to Calendar
Return
|
|
Consent-General Government   # 17.
|
Board of Supervisors |
General Services   |
|
|
Subject |
Adopt budget resolution adjusting the Yolo County Airport budget to reflect an increase of $289,421; approve contract with Teichert & Sons, Inc., for improvement work and repaving to taxiways at the Yolo County Airport for $263,110 through May 15, 2019; and authorize the Assistant County Administrator to amend the construction contract with Tiechert up to an additional $26,311 (10% of its original amount) and to extend the contract through June 30, 2019 should amendments be required by the scope of the project. (No general fund impact) (4/5 vote required) (Yarris) |
Recommended Action |
- Adopt budget resolution adjusting the Yolo County Airport 2018-2019 fiscal year operating budget to reflect an increase of $289,421;
- Approve contract with Teichert & Sons, Inc., for improvement work and repaving to taxiways at the Yolo County Airport for $263,110 through May 15, 2019; and
- Authorize the Assistant County Administrator to amend the construction contract with Teichert up to an additional $26,311 (10% of its original amount) and to extend the contract through June 30, 2019 should amendments be required by the scope of the project.
|
Strategic Plan Goal(s) |
Operational Excellence
Thriving Residents
Safe Communities
|
Reason for Recommended Action/Background |
In October of 2018, a request for proposal was submitted for improvements to and repaving of taxiways at the Yolo County Airport. This request for proposal included requests for bid amounts on three proposed options:
Option 1: Improvements to taxiways A and C.
Option 2: Improvements to taxiways A, B and C.
Option 3: Improvements to taxiways A, B, C and D.
Upon the receipt of bids and an assessment of available funding, Option 1 was selected. Teichert & Sons, Inc., has been awarded the contract with a bid of $263,110 for improvements on taxiways A and C. Funding for these improvements is in the process of being secured through a series of loans from CalTrans and the United States Department of Agriculture.
The contract issued to Teichert & Sons, Inc., is for the dollar amount identified in response to the request for proposal ($263,110) however, the General Services Department is requesting authorization for the Assistant County Administrator to issue amendments to their contract should the scope of work need to be altered. Amendments in excess of an addition $26,311 (10% construction contingency) will be brought to the Board of Supervisors for approval. |
Collaborations (including Board advisory groups and external partner agencies) |
County Administrator's Office, Department of Financial Services, County Counsel, General Services |
Competitive Bid Process |
Request for Proposals (RFP) Service Requested: Yolo County Airport Taxiways A-D Repaving Project
Bids Received
Bidder |
Bid |
Teichert & Sons |
$263,110 |
Vintage Paving |
$300,000 |
All bidding and awarding of contract for this work was done in compliance with Department of Financial Services Procurement policies and procedures. |
|
Fiscal Impact |
|
Source of Funds for this Expenditure |
|
Explanation (Expenditure and/or Revenue) |
Further explanation as needed: |
Funding for these improvements is being secured through a series of loans from CalTrans and the United States Department of Agriculture. |
|
|
|