  Consent-General Government   # 15.       
Board of Supervisors General Services  
Meeting Date: 11/20/2018  
Brief Title:    Central Library Archives Contract
From: Kevin Yarris, Director, General Services
Staff Contact: Laura Liddicoet, Sr. Administrative Services Analyst, General Services, x4881
Supervisorial District Impact:

Subject
Approve contract with Hometown Construction Inc., for construction work associated with the Central Library and Archives Renovation project for $536,000 through March 1, 2019; and authorize the Director of General Services to amend the construction contract with Hometown Construction Inc., up to an additional $53,600 (10% of its original amount) and to extend the contract through May 1, 2019 should amendments be required by the scope of the project. (No general fund impact) (Yarris)
Recommended Action
  1. Approve contract with Hometown Construction Inc., for construction work associated with the Central Library and Archives Renovation project for $536,000 through March 1, 2019; and
     
  2. Authorize the Director of General Services to amend the construction contract with Hometown Construction Inc., up to an additional $53,600 (10% of its original amount) and to extend the contract through May 1, 2019 should amendments be required by the scope of the project
Strategic Plan Goal(s)
Operational Excellence
Thriving Residents
Reason for Recommended Action/Background

In October of 2018, a request for proposal ("RFP") was advertised for improvement work at the Yolo County Central Library and Archives facility, located at 262 Buckeye Street in Woodland, CA. Four bids were received for this work, with Hometown Construction Inc., successfully earning the contract.  The contract issued to Hometown Construction, Inc., is for the dollar amount identified in response to the request for proposal ($536,000) however, the General Services Department is requesting authorization for the Director of General Services to issue amendments to their contract should the scope of work need to be altered.  Amendments in excess of an addition $53,600 (10% construction contingency) will be brought to the Board of Supervisors for approval.

A project budget was presented to the BOS on July 24, 2018, with the contract for purchase and installation of mobile compact shelving for this project being approved on September 11, 2018.

In October of 2016, the Board of Supervisors approved the 2017-2019 Capital Improvement Plan, which included necessary renovations and improvements to the Central Library and Archives in order to meet the adequate environmental controls to best preserve the County's archived collection. Design and engineering for the project occurred during the 2017-2018 fiscal year, with major construction scheduled for the 2018-2019 fiscal year. Renovations to the Central Library and Archives Center were conceptually approved by the Board of Supervisors on May 31, 2016, with additional financing requirements being addressed through the Yolo County Public Agencies Financing Authority 2017 Lease Revenue Bond Issuance.

Collaborations (including Board advisory groups and external partner agencies)

Yolo County Library, General Services Department, Department of Financial Services, County Counsel, County Administrator's Office

Competitive Bid Process
Request for Proposals (RFP) Service Requested: Yolo County Central Library Archives Remodel Project

Bids Received
 
Bidder Bid
American River, Inc. $694,000
Hometown Construction, Inc. $536,000
Monley Hamlin, Inc. $608,089
Tamarals Done Right Company $769,000
 
All bidding and awarding of contract for this work was done in compliance with Department of Financial Services Procurement policies and procedures.

Fiscal Impact
No Fiscal Impact
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   536,000
Amount budgeted for expenditure:    $   536,000
Additional expenditure authority needed:    $   0
On-going commitment (annual cost):    $  
Source of Funds for this Expenditure
$536,000
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
Funding for this contract has been secured through the Board of Supervisors approved 2017-2019 Capital Improvement Plan. Design and engineering for the project occurred during the 2017-2018 fiscal year, with major construction scheduled for the 2018-2019 fiscal year. Renovations to the Central Library and Archives Center were conceptually approved by the Board of Supervisors on May 31, 2016, with additional financing requirements being addressed through the Yolo County Public Agencies Financing Authority 2017 Lease Revenue Bond Issuance. A project budget was approved by the BOS on July 24, 2018.
Attachments
Att. A. Contract
Att. B. Bid Information
Att. C. Other Bids Received

Form Review
Inbox Reviewed By Date
Elisa Sabatini Elisa Sabatini 11/13/2018 12:40 PM
Financial Services (Originator) mpatterson 11/13/2018 02:10 PM
County Counsel Phil Pogledich 11/15/2018 02:01 PM
Form Started By: Laura Liddicoet Started On: 08/15/2018 10:01 AM
Final Approval Date: 11/15/2018

    