Print Reading Mode Back to Calendar Return
  Regular-General Government   # 40.       
Board of Supervisors County Administrator  
Meeting Date: 04/24/2018  
Brief Title:    Approve AB900 Main Jail Expansion & Renovation Project and Budget
From: Mindi Nunes, Assistant County Administrator, County Administrator’s Office
Staff Contact: Terry Vernon, Manager Capital Projects, County Administrator’s Office x8066
Supervisorial District Impact:

Subject
Approve AB900 Main Jail Expansion & Renovation plans and specifications and project budget of $43,981,907, approve agreement with Broward Builders for the construction of the Main Jail and Expansion and Renovation Project for an amount not to exceed $34,306,650. (No general fund impact) (Nunes/Vernon)
Recommended Action
  1. Approve AB900 Main Jail Expansion & Renovation project budget of $43,981,907 contingent on final approval from the State Department of Finance for grant proceeds in the amount of $36,295,000;
     
  2. Approve the Plans and Specifications for the Main Jail Expansion and Renovation Project; and
     
  3. Authorize the Assistant County Administrator to sign a construction agreement with Broward Builders for the construction of the Main Jail Expansion and Renovation Project for an amount not to exceed $34,306,650 (inclusive of change orders) and any additional documents related to the contract.
Strategic Plan Goal(s)
Safe Communities
Reason for Recommended Action/Background
In 2014, the Board adopted a resolution authorizing acceptance of local Jail Construction Financing (AB900) Phase II funds in the amount of $36,295,000 from the Board of State and Community Corrections. These funds were planned to be used to expand the current jail detention facility to include new housing, program space, kitchen and day reporting center. In addition renovations would be made to the existing footprint to provide for additional health and mental health beds, separate booking and intake and the security electronics upgrade retrofit.  The difference between the project budget of $43,981,907 and the grant of $36,295,000 includes the required 10% matching funds and additional project costs.  Funds have been set aside from Development Impact Fees, Accumulated Capital Outlay Funds, and County bond proceeds to complete the total project funding. The specifics of the funding for this project is outlined in the attached Budget Summary Table (Attachment A).

The Main Jail Expansion & Renovation Project (Monroe) is in the final stages of State approval prior to starting the construction phase of the project. In January 2018 the State Department of Finance approved the Construction documents for the bidding process. The project received bids March 1, 2018. The bids came back favorable with Broward Builders being the low bidder at $32,678,000.  The engineers estimate for construction was $36,340,033, thus the low bid represents a savings of $3,600,000 to the overall project budget.

Approval of this project budget and construction contract will allow the County to proceed with groundbreaking in late June and keep the project on track for State Department of Finance approval in June. With the State funding approval and the Board approved funds, no additional funding will be necessary.  The project milestone schedule is included as Attachment B and anticipates a Notice to Proceed from the State by end of June and occupancy June 2020.

Staff recommends approval of the total project budget of $43,981,907 including a not to exceed $34,306,650 construction contract and authorizing the Assistant County Administrator to execute the contract and any related documents.  This authority includes the ability sign change orders up to the not to exceed amount of $34,306,650.  Any change order that would exceed this amount would require Board approval.
Collaborations (including Board advisory groups and external partner agencies)
The County Administrator’s Office collaborated with the Yolo County Sheriff, County Counsel, County Department of Finance, California Board of State and Community Corrections (BSCC), California State Public Works Board, California Department of Corrections and Rehabilitation (CDCR), California Department of Finance (DOF) and the State Fire Marshall’s Office.
Competitive Bid Process
Bidding Process 
Project Plans & Specifications
Bidder Bid
Broward Builders* 32,673,000
Sletten Companies 34,698,800
Zovich 45,653,000

*Low Bidder

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   34,306,650
Amount budgeted for expenditure:    $   27,727,000
Additional expenditure authority needed:    $   0
On-going commitment (annual cost):    $  
Source of Funds for this Expenditure
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
The 2017-18 Adopted Budget included $27,727,000 for project construction costs. Remaining amounts will be included in the 2018-19 Budget.
Attachments
Att. A. Budget Summary
Att. B. Milestones
Att. C. Site Plan
Att. D. Contract

Form Review
Inbox Reviewed By Date
Financial Services Tom Haynes 04/19/2018 12:53 PM
County Counsel Phil Pogledich 04/19/2018 12:56 PM
Form Started By: jcross Started On: 04/06/2018 01:39 PM
Final Approval Date: 04/19/2018

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.