  Consent-General Government   # 11.       
Board of Supervisors General Services  
Meeting Date: 04/06/2021  
Brief Title:    Airport Drainage Basin Request for General Funds
From: Kevin Yarris, Director, General Services
Staff Contact: Lizbeth Garcia, Administrative Services Analyst, General Services, x4881
Supervisorial District Impact:

Subject
Adopt budget resolution adjusting the Yolo County Airport operating budget to reflect an increase of $99,480 from the general fund contingency and approve first amendment to Agreement No. 19-160 with Teichert & Sons Inc. for construction of the proposed Yolo County Airport Drainage Basin by an additional $99,480. (General fund impact $99,480) (4/5 vote required) (Yarris)
Recommended Action
  1. Adopt budget resolution adjusting the Yolo County Airport operating budget to reflect an increase of $99,480 from the general fund contingency; and
     
  2. Approve first amendment to Agreement No. 19-160 with Teichert & Sons INC. for construction of the proposed Yolo County Airport Drainage Basin by an additional $99,480.
Strategic Plan Goal(s)
In Support of All Goals (Internal Departments Only)
Reason for Recommended Action/Background
The Board approved a Federal Aviation Administration (FAA) grant application in May 2019 for construction of a Drainage Basin to meet the on-airport demands for storm runoff.  With the Board's approval, the County issued an RFP in May 2019 and received eight bids. Teichert & Sons, Inc., was awarded the contract in the amount of $884,610.

Since then, the Drainage Basin project has moved forward, and construction is completed. However, unforeseen delays affected the overall schedule of the project. Parachute company, Sky Dance, filed a lawsuit against the County stopping the project to comply with the court order.

Furthermore, additional work had to be completed which was not anticipated at the beginning of the project. The project required extra grading due to stubble left behind after harvesting. At this time, the General Services Department is asking the Board to approve an additional $99,480 in General Fund Contingency funding and approve an amendment to increase Teichert’s contract by $99,480 for a total compensation of $984,098.
Collaborations (including Board advisory groups and external partner agencies)
General Services Department, County Administrators Office, Department of Financial Services, County Counsel
Competitive Bid Process
N/A

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   99,480
Amount budgeted for expenditure:    $   0
Additional expenditure authority needed:    $   99,480
One-time commitment     Yes
Source of Funds for this Expenditure
$99,480
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
The attached budget resolution requests $99,480 in General Fund Contingency to cover the additional FY 20/21 expenses and  complete the administrative side the Drainage Basin Airport Project
Attachments
Att. A. Budget Resolution
Att. B. Amendment

Form Review
Inbox Reviewed By Date
Financial Services mpatterson 03/24/2021 03:38 PM
County Counsel Hope Welton 03/25/2021 08:40 AM
Form Started By: lgarcia Started On: 03/02/2021 04:13 PM
Final Approval Date: 03/30/2021

    