Print Reading Mode Back to Calendar Return
  Consent-Community Services   # 21.       
Board of Supervisors Meeting   
Meeting Date: 04/07/2015  
Brief Title:    CR 86A Bridge Replacement at Cottonwood Slough
From: Taro Echiburu, Director, Planning, Public Works and Environmental Services
Staff Contact: Mark Christison, Associate Civil Engineer, Planning, Public Works and Environmental Services Department, x8842
Supervisorial District Impact:

Subject
Adopt plans and specifications for the replacement of the County Road 86A Bridge over Cottonwood Slough. (No general fund impact) (Echiburu/Christison)
Recommended Action
  1. Adopt plans and specifications for the replacement of the County Road 86A Bridge over Cottonwood Slough (No general fund impact).
     
  2. Authorize the Assistant Director for Public Works to sign the Notice to Contractors.
     
  3. Authorize the Department of Planning, Public Works, and Environmental Services to advertise for competitive bids once authorization to proceed with construction is approved by Caltrans.
     
  4. Authorize the Director of Planning, Public Works, and Environmental Services or the Assistant Director for Public Works to execute a construction contract with the lowest responsive bidder, provided the contract amount does not exceed available funds, or to reject all bids.
     
  5. Authorize the Director of Planning, Public Works, and Environmental Services or the Assistant Director for Public Works to approve all construction change orders, provided the contract amount does not exceed available funds for the project.
Strategic Plan Goal(s)
Preserve and support agriculture
Provide fiscally sound, dynamic and responsive services
Reason for Recommended Action/Background
These actions will allow the department to solicit competitive bids, expedite the contract award, and promptly proceed with construction. The bridge is located on County Road 86A over Cottonwood Slough, 0.22 miles north of County Road 25 south of the Town of Esparto. Due to streambed degradation from Cottonwood Slough significant scour exists at all of the existing abutment and pier footings. Caltrans has classified the bridge as functionally obsolete with foundational scour issues, with a sufficiency rating of 49.8 out of 100. The construction phase of the project is eligible for federal Highway Bridge Program funds at a reimbursement rate of 100%. A ‘request for authorization’ of construction funds was submitted to Caltrans on March 10, 2015. In order to remain eligible for federal funds, advertisement for bidding cannot begin prior to Caltrans authorization. $1,691,000 in federal funds are programmed in SACOG’s Metropolitan Transportation Improvement Plan for construction and construction engineering; staff will work with Caltrans to update funding after bids are received, to ensure full reimbursement of costs. The bridge replacement project is expected to be completed by the end of the summer construction season, provided Caltrans authorization is approved by the end of April. Due to environmental mitigation and permit requirements, work in the slough is restricted to the period from June 1 to October 31. Ideally, construction work will start on or near the June 1 date, to allow the contractor the maximum construction season. The recommended action will allow the department to act in a timely manner when authorization is received.
Collaborations (including Board advisory groups and external partner agencies)
Federal Highway Administration, Caltrans Sacramento Area Council of Governments (SACOG), California Department of Fish and Wildlife, California Regional Water Quality Control Board, U.S. Fish and Wildlife Service, U.S. Army Corps of Engineers.

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   1,691,000
Amount budgeted for expenditure:    $   1,691,000
Additional expenditure authority needed:    $   0
One-time commitment     Yes
Source of Funds for this Expenditure
$0
Explanation (Expenditure and/or Revenue)
Further explanation as needed:
The construction phase of the project is eligible for federal Highway Bridge Program funds at a reimbursement rate of 100%.
Attachments
Att. A. Location Map
Att. B. Notice to Contractors
Att. C. Photographs

Form Review
Inbox Reviewed By Date
County Counsel Phil Pogledich 04/01/2015 09:44 PM
Form Started By: Mark Christison Started On: 03/24/2015 01:18 PM
Final Approval Date: 04/01/2015

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.