Print Reading Mode Back to Calendar Return
  Consent-Community Services   # 24.       
Board of Supervisors   
Meeting Date: 03/24/2020  
Brief Title:    Budget Resolution for Installation of a Fiber Optic Network at the Landfill
From: Taro Echiburu, Director, Department of Community Services
Staff Contact: Rick Moore, Principal Civil Engineer, Department of Community Services, x8859
Supervisorial District Impact:

Subject
Adopt a budget resolution increasing the Department of Community Services budget by $80,750 (for a total appropriation of $39,821,574) to fund the installation of a fiber optic network at the Yolo County Central Landfill. (No general fund impact) (4/5 vote required) (Echiburu/Moore)
Recommended Action
Adopt a budget resolution increasing the Department of Community Services budget by $80,750 (for a total appropriation of $39,821,574) to fund the installation of a fiber optic network at the Yolo County Central Landfill.
Strategic Plan Goal(s)
Safe Communities
  • Outcome: Enhance infrastructure and reduce flood risk in the unincorporated areas of Yolo County.
  • Strategy: Establish access for wireless point providers to utilize the tower at the Yolo County Central Landfill by June 30, 2020.)
Reason for Recommended Action/Background
Following a competitive solicitation process, a contract was awarded to MP Nexlevel on September 4, 2018 (Agreement No. PO3431), in the amount of $80,750 to install a fiber optic network at the Yolo County Central Landfill. It was anticipated that the project would be completed in fiscal year 2018-19, and as such, sufficient funds were budgeted in fiscal year 2018-19. A delay in the preparatory work delayed the start of this project and pushed the start date into fiscal year 2019-2020. At the time the 2019-2020 budget was being finalized, this project was anticipated to be completed before June 30th and project funds were not budgeted for 2019-2020. In order to correct this and complete the project, staff is requesting an adjustment to this fiscal year’s budget in the previously stated amount.
Collaborations (including Board advisory groups and external partner agencies)
Staff has collaborated with County Counsel in the preparation of the Budget Resolution.
Competitive Bid Process
A competitive bid process was conducted prior to award of the contract.  Bids were opened on September 4, 2018 and results are shown below:
 
Consolidated Networks Corporation $75,586.00 (disqualified)
MP Nexlevel of California, Inc. $80,750.00
Westech Industries, Inc. $83,087.00

Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
Total cost of recommended action:    $   80,750
Amount budgeted for expenditure:    $   0
Additional expenditure authority needed:    $   80,750
One-time commitment     Yes
Source of Funds for this Expenditure
$80,750
Attachments
Att. A. Budget Resolution

Form Review
Inbox Reviewed By Date
Financial Services Shelby Milliren 03/09/2020 03:50 PM
County Counsel Hope Welton 03/09/2020 03:52 PM
Form Started By: rmoore Started On: 03/09/2020 11:16 AM
Final Approval Date: 03/12/2020

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.